Wednesday, 13 February 2013

Day 128 - Painted into a corner

Day 128, and the north side of the house has been fully painted.
Also the downpipes have been connected.

View from the northeast.  Eastern side of the house is not yet painted, alas.

Nor, for that matter, is the south side!

However, all the scaffolding is finally down, allowing an unhindered view of the house for the first time.
View of the front entrance:

Inside, there are several boxes of door handles.
And doors in which they will eventually reside, arrayed like some sort of surrealist art installation:


The interior has been pretty much fully painted at this stage.  Wall color is Half Tea.  Here is the garage:


 The moldings are looking quite spiffy:

Living room area:


 View from the kitchen, towards front door:

 View from front door in towards kitchen, with it's Jalapeno paint job:


View from living room, down hall towards garage:


 View of dining room from kitchen:



 View of living area and kitchen from the hallway. 

The kitchen itself should be arriving around Friday, with installation early next week.  I suspect that means that the electrics will be fitted in either late this week or early next.  Bathroom tiles likely to go down late next week.  The rest of the flooring will follow, once all the tradespeople have finished everything that requires them to tromp back and forth around the place.

Not long now!